Sprint 7 Review

Sprint 7 Goal (6/18/25 - 7/1/25):

•Finalize AC2 code, team focus on the build (login, create new time record, save time record, logout) completed and ready for QA testing. Set up UAT domain and ensure it can be accessed with a test ID.

•Actual: Login with selecting a database and logout are completed and to the QA environment ready for testing. The UAT domain is set up, user IDs still need to be assigned to this environment. AC2 code still pending. Blocker with create new time record on the programs and services activity picker/filtering.

Sprint 8 Goal (7/2/25 – 7/15/25):

•Finalize AC2 code, team focus on the build (create new time record) completed and ready for QA testing, remediate issues with the programs and services activity picker.

Categories: #SprintReviewUpdate
Share Sprint 7 Review on Facebook Share Sprint 7 Review on X (formerly Twitter) Share Sprint 7 Review on Linkedin Email Sprint 7 Review link

The Time Entry Transformation has officially ended. Continue reporting web app issues to the SSIS Help Desk

We will remediate defects as they arise. The Case Load Button is the last major enhancement and will be released on Aug. 18, 2026. Currently, there are no plans for additional enhancements. 