Sprint Review 6
Sprint 6 Goal (6/4/25 – 6/17/25):
Save a complete time record in the QA environment. Finalize AC2 code and production domain/URL.
Actual: QA has blockers in this environment, AC2 code is still pending with escalation involved to push completion, production domain/URL has been determined by business leadership and signed off by communications (https://time.ssis.mn.gov)
Sprint 7 Goal (6/18/25 – 7/1/25):
Finalize AC2 code, team focus on the build (login, create new time record, save time record, logout) completed and ready for QA testing. Set up UAT domain and ensure it can be accessed with a test ID.