Sprint Review 11
Here’s what we’re working on right now in Sprint 11, as we get ready for Sprint 12, which starts on August 27th with the UAT kick-off:
Final MVP1 Items with DEV
- Fixing the last few defects
Final Testing, Security, and Analytics
- QA Functional Testing
- Accessibility Testing
- Performance Testing
- SiteImprove Analytics
- Finalizing OKR (Objectives & Key Results) Baselines and Goals
UAT Prep Work
- Finalizing test instructions and test cases
- Creating email templates to send out access info to testers
Pilot Prep Work
- Thanks to Stearns County - our first pilot agency!
- Communications and confirming list of users with Stearns for our first pilot rollout planned for sprint 13.