Sprint Review 11

Here’s what we’re working on right now in Sprint 11, as we get ready for Sprint 12, which starts on August 27th with the UAT kick-off:

Final MVP1 Items with DEV

  • Fixing the last few defects

Final Testing, Security, and Analytics

  • QA Functional Testing
  • Accessibility Testing
  • Performance Testing
  • SiteImprove Analytics
  • Finalizing OKR (Objectives & Key Results) Baselines and Goals

UAT Prep Work

  • Finalizing test instructions and test cases
  • Creating email templates to send out access info to testers

Pilot Prep Work

  • Thanks to Stearns County - our first pilot agency!
  • Communications and confirming list of users with Stearns for our first pilot rollout planned for sprint 13.
Categories: #sprintreview
Share Sprint Review 11 on Facebook Share Sprint Review 11 on Twitter Share Sprint Review 11 on Linkedin Email Sprint Review 11 link