  • Sprint Review 12

    Share Sprint Review 12 on Facebook Share Sprint Review 12 on Twitter Share Sprint Review 12 on Linkedin Email Sprint Review 12 link

    Sprint 11 Goal (8/13/25 – 8/26/25):

    • Team focus is on completing all open development and testing tasks to prepare for UAT external user testing and kick-off for sprint 12 starting 8/27/25. Process documentation for how to manually update the UAT environment, last items for business rules filtering, and error handling will move forward to Sprint 11 from Sprint 10 to complete.

    • Actual Results: All tasks were completed with development and testing for UAT, and we successfully completed the last items for business rules filtering. We have some error handling backend documentation moving to sprint 12. We kicked off UAT today and have some testers already accessing the site to provide feedback!

    Sprint 12 Goal (8/27/25 – 9/9/25)

    • Validation on the backend for the APIs and Service Calls in all environments. Fine tune session state (log-in, log-out). Auto-populate with respect to the regarding section, activity log, design the draft and discuss where the drafts will be stored. Continue to work through UAT defects and build updates. Plan for Sprint 13 to Pilot in Production with internal county workers first, which is approximately 115 users. Big thanks to Cassie for helping coordinate and to Stearns County for agreeing to be our first pilot agency!
  • Sprint Review 11

    Share Sprint Review 11 on Facebook Share Sprint Review 11 on Twitter Share Sprint Review 11 on Linkedin Email Sprint Review 11 link

    Here’s what we’re working on right now in Sprint 11, as we get ready for Sprint 12, which starts on August 27th with the UAT kick-off:

    Final MVP1 Items with DEV

    • Fixing the last few defects

    Final Testing, Security, and Analytics

    • QA Functional Testing
    • Accessibility Testing
    • Performance Testing
    • SiteImprove Analytics
    • Finalizing OKR (Objectives & Key Results) Baselines and Goals

    UAT Prep Work

    • Finalizing test instructions and test cases
    • Creating email templates to send out access info to testers

    Pilot Prep Work

    • Thanks to Stearns County - our first pilot agency!
    • Communications and confirming list of users with Stearns for our first pilot rollout planned for sprint 13.
  • Sprint Review 10

    Share Sprint Review 10 on Facebook Share Sprint Review 10 on Twitter Share Sprint Review 10 on Linkedin Email Sprint Review 10 link

    Welcome, Summary of Progress, and What’s Next

    •Sam Breidenbach – Product Manager - Time Entry Transformation

    Sprint 10 Goal (7/30/25 – 8/12/25):

    •Team focus on the build (create new time record) with business rules and filtering completed and ready for QA testing. Complete user access to the Training environment, complete the process documentation for how to manually update the UAT environment and create new branches for UAT, Training, and Production.

    •Actual: The Create New Time Record build is complete, with business rules and filtering very close as of end of sprint yesterday. New branches were created, and internal state user access was completed for UAT. The Training environment is not needed going forward by the Learning & Development Team and can use UAT for their purposes.

  • Sprint 9 Review

    Share Sprint 9 Review on Facebook Share Sprint 9 Review on Twitter Share Sprint 9 Review on Linkedin Email Sprint 9 Review link

    Sprint 9 Goal (7/16/25 – 7/29/25):

    •Team focus on the build (create new time record) with business rules and filtering completed and ready for QA testing. Promote Login, Logout screens to UAT environment, and complete the Training environment build.

    •Actual: Login, and Logout screens were both promoted to the UAT environment with light testing completed by QA and product manager, the Training environment build was completed.

    Sprint 10 Goal (7/30/25 – 8/12/25):

    •New goal: Team focus on the build (create new time record) with business rules and filtering completed and ready for QA testing. Complete user access to the Training environment, complete the process documentation for how to manually update the UAT environment and create new branches for UAT, Training, and Production.

  • Sprint 8 Review

    Share Sprint 8 Review on Facebook Share Sprint 8 Review on Twitter Share Sprint 8 Review on Linkedin Email Sprint 8 Review link

    Sprint 8 Goal (7/2/25 – 7/15/25):

    •Team focus on the build (create new time record) completed and ready for QA testing, remediate issues with the programs and services activity picker.

    •Actual: Outstanding items from Sprint 7 were completed to finalize the AC2 code, login and logout screens are developed/functional in multiple environments, and most of the create new time record screen is complete. Development work continues for the programs, services, and activity dropdown filtering.

    Sprint 9 Goal (7/16/25 – 7/29/25):

    •Team focus on the build (create new time record) with business rules and filtering completed and ready for QA testing. Promote Login, Logout screens to UAT environment, and complete the training environment build.