Sprint 9 Goal (7/16/25 – 7/29/25):

•Team focus on the build (create new time record) with business rules and filtering completed and ready for QA testing. Promote Login, Logout screens to UAT environment, and complete the Training environment build.

•Actual: Login, and Logout screens were both promoted to the UAT environment with light testing completed by QA and product manager, the Training environment build was completed.

Sprint 10 Goal (7/30/25 – 8/12/25):

•New goal: Team focus on the build (create new time record) with business rules and filtering completed and ready for QA testing. Complete user access to the Training environment, complete the process documentation for how to manually update the UAT environment and create new branches for UAT, Training, and Production.

Categories: #sprintreview
Share Sprint 9 Review on Facebook Share Sprint 9 Review on X (formerly Twitter) Share Sprint 9 Review on Linkedin Email Sprint 9 Review link

The Time Entry Transformation has officially ended. Continue reporting web app issues to the SSIS Help Desk

We will remediate defects as they arise. The Case Load Button is the last major enhancement and will be released on Aug. 18, 2026. Currently, there are no plans for additional enhancements. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>