Sprint Review 14

Sprint 14 Goal (10/1/25 – 10/21/25)

•Round 2 pilot testing with Brown, Freeborn, Meeker, Nicollet, Scott and remediate reported defects, encourage more Stearns County users to try the web app. Complete QA functional testing and PDM testing of activity log, including searching for records, sign-off toggle, navigation from log to create new record, new actions menu. Start design on how drafts are listed and selected from the grid and how time records will be viewed. Auto-populate the Regarding section for single-client participant workgroups. Design and frontend development work for the system downtime banner to alert users of scheduled maintenance work.

•Actual: Round 2 of pilot testing was completed and more users have been trying the web app. Activity log functionality for basic search is completed with searching for records, sign-off toggle, and navigation. The design of drafts were worked through and discussion on how records will be viewed, with validation needed as part of user experience research. Auto-populate single-client workgroups completed.

Sprint 15 Goal (10/22/25 – 11/11/25):

•New goal: Add action button to activity log so users can Sign Off and View records, make the activity log the landing page, complete the system downtime banner development work and QA functional testing. All activity log work completed and through QA functional testing, ready for UAT deployment with the next sprint.

Categories: #sprintreview
Share Sprint Review 14 on Facebook Share Sprint Review 14 on Twitter Share Sprint Review 14 on Linkedin Email Sprint Review 14 link